A. total duration of project is reduced
B. total duration of project is increased
C. uniform demand of resources is achieved
D. cost of project is controlled
Correct Answer: uniform demand of resources is achieved ✔
Last Updated: January 19, 2019
A. total duration of project is reduced
B. total duration of project is increased
C. uniform demand of resources is achieved
D. cost of project is controlled
Correct Answer: uniform demand of resources is achieved ✔
Last Updated: January 19, 2019