The direct cost of a project with respect to normal time is________________?
Related MCQs
Economic saving of time results by crashing__________?
Slack time refers to__________?
The constraints in case of resource smoothening operation would be__________?
Crash project duration is obtained by summing the__________?
Which of the following earth moving machines has the shortest cycle time?
For a given size of bucket, the ideal output of a dragline will be least in__________?
Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing Reason R: If the angle of swing is decreased, the cycle time will be decreased__________?
An excavator costs Rs. 20,00,000/- and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is__________?
Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?
Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?
The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to__________?
A four wheel trac*or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be__________?
If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be__________?
A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be__________?
If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be__________?
In the bar chart planning__________?
At a work site, statistical quality control of concrete means__________?
In time-cost optimization of a project, crashing is done__________?
Mobilization advance up to 10% of the cost of work is given to a contractor__________?
A contractor has two options : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he__________?
The original cost of an equipment is Rs.10,000/-. Its salvage value at the end of its total useful life of five years is Rs. 1,000/-. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be__________?
The correct sequence of these activities is__________?
For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is__________?
Grader is used mainly for__________?
The most suitable type of equipment for compaction of cohesive soils is__________?
The basic action involved in sheep foot rolling is__________?
Preliminary project report for a road project must contain__________?
Sensitivity analysis is a study of__________?
Wheeled tractors are replacing crawler tractors because__________?
In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having__________?
The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted, and pneumatic tyremounted machines would be respectively__________?
Batching refers to__________?
For excavating utility trenches with precise control of depth, the excavation equipment used is__________?
Which one of the following is not an excavating and moving type of equipment ?
The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is__________?
The correct sequence of these operations in tunnel construction is__________?
PERT is preferred for planning because of__________?
In resources levelling__________?
Sinking fund is__________?
During the construction period, price variation clause in contracts caters to__________?
The time corresponding to minimum total project cost is__________?
In the critical path method of construction planning, Free Float can be__________?
A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be__________?
If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is__________?
The probability of completion of any activity within its expected time is__________?
An earth moving equipment costs Rs. 5,00,000/- and has an estimated life of 10 years and a salvage value of Rs. 50,000/-.What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069 ?
A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is: Drive wheels : 25000 kg Scraper wheels : 10000 kg If the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is__________?
If the gross vehicle weight of a truck is 30 t and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is__________?
Rolling resistance of a wheel depends upon__________?
If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is__________?
A machine is purchased for Rs. 10,000,00/- and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000/-. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is__________?
The direct cost of a project with respect to normal time is________________?
A. minimum
B. maximum
C. zero
D. infinite
Correct Answer:
minimum
✔