The normal time required for the completion of project in the above problem is_______________?
Related MCQs
The process of incorporating changes and rescheduling or replanning is called__________?
The reduction in project time normally results in__________?
The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as__________?
A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be__________?
Critical path__________?
Whenever an activity has zero total float, then__________?
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then__________?
Latest start of an activity is always__________?
Which of the following does not represent an activity?
The area under the Beta – distribution curve is divided into two equal parts by__________?
Which of the following is not a PERT event ?
Which of the following is a weakness of bar chart ?
The normal time required for the completion of project in the above problem is_______________?
A. 9 days
B. 13 days
C. 14 days
D. 19 days
Correct Answer:
14 days
✔