For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is_______________?
Related MCQs
The expected out turn of half brick partition wall per mason per day is__________?
The slope of the outlet of ‘P trap’ below the horizontal is kept__________?
Pick up the incorrect statement from the following?
Pick up the incorrect statement from the following?
Pick up the correct statement in case of water supply ?
Pick up the correct statement from the following?
Pick up the incorrect statement from the following ?
Pick up the correct statement from the following ?
Pick up the correct statement from the following?
Pick up the correct statement from the following?
Pick up the incorrect statement from the following?
Referring of given figure, pick up the correct statement from the following?
Pick up the correct statement from the following?
Pick up the correct statement from the following?
Berms are provided in canals if these are__________?
The weight of an item is measured correct to nearest__________?
The floor area includes the area of the balcony up to__________?
Size, capacity and materials need be specified for__________?
88 is 1400 kg/cm2 and bond stress is 6 kg/cm2, the If tensile stress of a steel rod of diameter required bond length of the rod is__________?
The volume is measured correct to the nearest__________?
The damp proof course (D.P.C.) is measured in__________?
The item of steel work which is measured in sq.m, is__________?
The brick work is measured in sq metre, in case of__________?
The expected out turn for earth work in excavation in ordinary soil per workman per day is__________?
The minimum width of a septic tank is taken__________?
Pick up the item of work not included in the plinth area estimate__________?
If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is__________?
period in a septic tank is assumed__________?
Pick up the incorrect statement regarding a master trap from the following ?
The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended__________?
Pick up the correct statement from the following?
The correct Prismoidal formula for volume is__________?
The order of booking dimensions is__________?
The unit of measurement is per quintal for the following?
The ‘centre line method’ is specially adopted for estimating__________?
The inspection pit or chamber is a manhole provided in a base drainage system__________?
In case of laying gullies, siphons, intercepting traps, the cost includes__________?
Carpet area does not include the area of__________?
The expected out turn of 12 mm plastering with cement mortar is__________?
The measurement is made for stone work in square metre in case of__________?
The total length of a cranked bar through a distance D. at 45° in case of a beam of effective length L, is__________?
The concrete work for the following part of the building of specified thickness is measured in square metres__________?
A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved ?
Anti-siphonage pipe is connected to__________?
The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is__________?
The item of the brick structure measured in sq.m, is__________?
According to ISI method of measurement, the order of the sequence is__________?
The most reliable estimate is__________?
While preparing a detailed estimate__________?
The expected out turn of 2.5 cm cement concrete floor per mansion per day__________?
Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds__________?
For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is_______________?
A. 0.90 m3
B. 0.94 m3
C. 0.98 m3
D. 1.00 m3
Correct Answer:
0.94 m3
✔
Last Updated:
January 20, 2019