Logo

A. 13
B. 11
C. 12
D. 15

A completes 2*(1/8) = 1/4th of the work 2/3rd of the remaining work
= (3/4) * (2/3) = 1/2 B completes 1/2 of the work in
(1/2)÷(1/14) = 7 days C completes 1/4th of the work in
(1/4)÷(1/16) = 4 days They take 13 days to complete the work

Correct Answer: A. 13

Last Updated: November 19, 2019