Work done by P in 1 day = 1/24
Work done by Q in 1 day = 1/9
Work done by R in 1 day = 1/12
Work done by Q and R in 1 day = 1/9 + 1/12 = 7/36
Work done by Q and R in 3 days = 3×7/36 = 7/12
Remaining work = 1 – 7/12 = 5/12
Number of days in which P can finish the remaining work = (5/12) / (1/24) = 10

Correct Answer: A. 10