Logo

A. 8
B. 6
C. 4
D. 2

Work done by P in 1 day = 1/18
Work done by Q in 1 day = 1/15
Work done by Q in 10 days = 10/15 = 2/3
Remaining work = 1 – 2/3 = 1/3
Number of days in which P can finish the remaining work = (1/3) / (1/18) = 6

Correct Answer: B. 6

Last Updated: February 07, 2020