Amount of work P can do in 1 day = 1/16
Amount of work Q can do in 1 day = 1/12
Amount of work P, Q and R can together do in 1 day = 1/4
Amount of work R can do in 1 day = 1/4 – (1/16 + 1/12) = 3/16 – 1/12 = 5/48
=> Hence R can do the job on 48/5 days = 9 (3/5) days

Correct Answer: A. 9(3/5) days