A. 3 days
B. 4 days
C. 6 days
D. 8 days
Submitted by: মোঃ আশাদুজ্জামান
Solution:
12×16×C=12×8×A
Or, A:C=2:1 [Efficiency ratio]
Let, Required time be T days
Applying MDH Method:
12×8×2=16×2×3+(6×2+4×1)×T
Or, 192=96+14T
Or, T=6
Answer:6 days
Correct Answer: 6 days ✔