A. CPA (Critical Path Analysis)
B. CPP (Critical Path Plotted)
C. MCE (Minimum Cost Expenditure)
D. CPS (Critical Path Scheduling)
E. all of the above
Correct Answer: all of the above ✔
Last Updated: January 28, 2019
A. CPA (Critical Path Analysis)
B. CPP (Critical Path Plotted)
C. MCE (Minimum Cost Expenditure)
D. CPS (Critical Path Scheduling)
E. all of the above
Correct Answer: all of the above ✔
Last Updated: January 28, 2019