A. bar chart method
B. milestone chart
C. critical path method (CPM)
D. programme evaluation and review technique (PERT)
E. none of the above
Correct Answer: bar chart method ✔
Last Updated: January 28, 2019
A. bar chart method
B. milestone chart
C. critical path method (CPM)
D. programme evaluation and review technique (PERT)
E. none of the above
Correct Answer: bar chart method ✔