A. An application-composition model
B. A post-architecture model
C. A reuse model
D. An early design model

Explanation: Estimates are based on function points, which are then converted to number of lines of source code. The formula follows the standard form discussed above with a simplified set of seven multipliers.

Correct Answer: An early design model