Logo

A. The difficulty of the problem to be solved
B. High frustration caused by personal, business, or technological factors that causes friction among team members
C. The degree of sociability required for the project
D. The rigidity of the delivery date
c
Explanation: Development is irrelevant of social quotient.

Correct Answer: The degree of sociability required for the project

Last Updated: February 04, 2019