Option A: 1.00 m
Option B: 1.25 m
Option C: 1.5 m
Option D: 2.0 m
Correct Answer: 1.25 m ✔
Click for More Details
Option A: A critical path always begins at the very first event
Option B: A critical path always terminates at the last event
Option C: Critical activities control the project duration
Option D: Critical activity is the one for which free float is zero
Correct Answer: Critical activity is the one for which free float is zero ✔
Click for More Details
Option A: Start float and finish float are always equal
Option B: Total float can be either start float or finish float
Option C: Start float and finish float need not be equal
Option D: Start float and finish float are the differences between activity times and not event times
Correct Answer: Start float and finish float need not be equal ✔
Click for More Details
Option A: Earliest start of an activity is the early event time of the node it leaves.
Option B: Latest finish of an activity is the late event time of the node it enters.
Option C: Latest start of an activity is its latest finish minus its duration.
Option D: none of the above
Correct Answer: none of the above ✔
Click for More Details
Option A: small projects
Option B: large and complex projects
Option C: research and development projects
Option D: deterministic activities
Correct Answer: research and development projects ✔
Click for More Details
Option A: Activity arrows in a CPM network are drawn to scale
Option B: The tail of an arrow represents the finish of an activity
Option C: Arrow bead represents the start of an activity
Option D: none of the above
Correct Answer: none of the above ✔
Click for More Details
Option A: normal distribution curve
Option B: Poisson’s distribution curve
Option C: Beta – distribution curve
Option D: none of the above
Correct Answer: Beta – distribution curve ✔
Click for More Details
Option A: greater than earliest event time of the following node
Option B: less than earliest event time of the following node
Option C: less than or equal to earliest event time of the following node
Option D: greater than or equal to earliest event time of the following node
Correct Answer: less than or equal to earliest event time of the following node ✔
Click for More Details
Option A: 3.5 and 5/6
Option B: 5 and 25/36
Option C: 3.5 and 25/36
Option D: 4 and 5/6
Correct Answer: 5 and 25/36 ✔
Click for More Details
Option A: identify the activities which can be delayed without affecting the total float of preceding activity
Option B: identify the activities, which can be delayed without affecting the total float of succeeding activity
Option C: establish priorities
Option D: identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
Correct Answer: identify the activities, which can be delayed without affecting the total float of succeeding activity ✔
Click for More Details
Option A: its latest finish time and earliest start time for its successor activity
Option B: its latest start time and earliest start time
Option C: its latest start time and earliest finish time
Option D: its earliest finish time and earliest start time for its successor activity
Correct Answer: its latest start time and earliest start time ✔
Click for More Details
Option A: its earliest finish time and earliest start time for its successor activity
Option B: its latest start time and earliest start time
Option C: its latest finish time and earliest start time for its successor activity
Option D: its earliest finish time and latest start time for its successor activity
Correct Answer: its earliest finish time and earliest start time for its successor activity ✔
Click for More Details
Option A: preceding activities
Option B: succeeding activities
Option C: the particular activity involved
Option D: none of the above
Correct Answer: the particular activity involved ✔
Click for More Details
Option A: crash time
Option B: normal time
Option C: optimistic time
Option D: standard time
Correct Answer: normal time ✔
Click for More Details
Option A: minimum
Option B: maximum
Option C: zero
Option D: infinite
Correct Answer: minimum ✔
Click for More Details
Option A: cheapest critical activity
Option B: cheapest non-critical activity
Option C: costliest critical activity
Option D: costliest non-critical activity
Correct Answer: cheapest critical activity ✔
Click for More Details
Option A: an activity
Option B: an event
Option C: both event and activity
Option D: none of the above
Correct Answer: an event ✔
Click for More Details
Option A: resources
Option B: project duration time
Option C: both resources and project duration time
Option D: none of the above
Correct Answer: project duration time ✔
Click for More Details
Option A: normal durations for all the activities
Option B: crash durations for all activities
Option C: crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
Option D: crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Correct Answer: crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities ✔
Click for More Details
Option A: Drag line
Option B: Hoe
Option C: Clam shell
Option D: Dipper shovel
Correct Answer: Dipper shovel ✔
Click for More Details
Option A: Moist loam
Option B: Sand and gravel
Option C: Good common earth
Option D: Wet sticky clay
Correct Answer: Wet sticky clay ✔
Click for More Details
Option A: Both A and R are true and R is the correct explanation of A
Option B: Both A and R are true but R is not the correct explanation of A
Option C: A is true but R is false
Option D: A is false but R is true
Correct Answer: Both A and R are true and R is the correct explanation of A ✔
Click for More Details
Option A: Rs. 8,43,750/-
Option B: Rs. 8,75,000/-
Option C: Rs. 10,50,000/-
Option D: Rs. 11,56,250/-
Correct Answer: Rs. 8,43,750/- ✔
Click for More Details
Option A: Ice
Option B: Concrete
Option C: Loose sand
Option D: Earth
Correct Answer: Earth ✔
Click for More Details
Option A: Concrete
Option B: Loose sand
Option C: Asphalt
Option D: Firm earth
Correct Answer: Loose sand ✔
Click for More Details
Option A: 2 kg/tonne
Option B: 6 kg/tonne
Option C: 9 kg/tonne
Option D: 20 kg/tonne
Correct Answer: 9 kg/tonne ✔
Click for More Details
Option A: 20 kg/tonne
Option B: 30 kg/tonne
Option C: 40 kg/tonne
Option D: 50 kg/tonne
Correct Answer: 40 kg/tonne ✔
Click for More Details
Option A: 50%
Option B: less than 50%
Option C: more than 50%
Option D: 100%
Correct Answer: 50% ✔
Click for More Details
Option A: Rs.1740
Option B: Rs.3480
Option C: Rs.5220
Option D: Rs.6960
Correct Answer: Rs.3480 ✔
Click for More Details
Option A: 2.3% and 84.1%
Option B: 97.7% and 84.1%
Option C: 97.7 % and 15.9%
Option D: 15.9% and 97.7%
Correct Answer: 2.3% and 84.1% ✔
Click for More Details
Option A: 1,2 and 3 are correct
Option B: 1 and 4 are correct
Option C: 2, 3 and 4 are correct
Option D: 1,2 and 4 are correct
Correct Answer: 1 and 4 are correct ✔
Click for More Details
Option A: measurement of risks to eliminate failures
Option B: applying the theory’ of probability to sample testing or inspection
Option C: reduction in wastage of inspection costs
Option D: reduction in costs for the removal of defects
Correct Answer: applying the theory’ of probability to sample testing or inspection ✔
Click for More Details
Option A: on all the activities
Option B: on all the activities lying on the critical path
Option C: only on activities lying on the orginal critical path and having flatter cost slopes
Option D: on original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
Correct Answer: on original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope ✔
Click for More Details
Option A: on commencement of work at site for payment of loan taken by him
Option B: for the purchase of construction materials
Option C: for the payment of advances to labour and other staff
Option D: for all activities required to start the work at site on finalization of the contract document
Correct Answer: for all activities required to start the work at site on finalization of the contract document ✔
Click for More Details
Option A: should invest in neither of the two projects
Option B: could invest in either of the two projects
Option C: should invest in project A
Option D: should invest in project B
Correct Answer: should invest in neither of the two projects ✔
Click for More Details
Option A: Rs. 8,800/-
Option B: Rs. 7,600/-
Option C: Rs. 6,400/-
Option D: Rs. 5,000/-
Correct Answer: Rs. 6,400/- ✔
Click for More Details
Option A: 1,3,2,4
Option B: 3,1,4,2
Option C: 3,1,2,4
Option D: 1,3,4, 2
Correct Answer: 3,1,2,4 ✔
Click for More Details
Option A: 8 days
Option B: 9 days
Option C: 10 days
Option D: 15 days
Correct Answer: 9 days ✔
Click for More Details
Option A: trimming and finishing
Option B: shaping and trimming
Option C: finishing and shaping
Option D: finishing, shaping and trimming
Correct Answer: shaping and trimming ✔
Click for More Details
Option A: Smooth-wheeled rollers
Option B: Vibratory rollers
Option C: Sheep foot rollers
Option D: Tampers
Correct Answer: Sheep foot rollers ✔
Click for More Details
Option A: Kneading
Option B: Pressing
Option C: Tamping
Option D: Vibration
Correct Answer: Kneading ✔
Click for More Details
Option A: the detailed estimated cost based on detailed design
Option B: the several alternatives of the project that have been considered
Option C: the soil survey, traffic survey, concept design and approximate cost
Option D: the contract documents for inviting tenders
Correct Answer: the soil survey, traffic survey, concept design and approximate cost ✔
Click for More Details
Option A: comparison of profit and loss
Option B: comparison of assets and liabilities
Option C: change in output due to change in input
Option D: economics of cost and benefits of the project
Correct Answer: change in output due to change in input ✔
Click for More Details
Option A: 1,3 and 4 are correct
Option B: 2, 3 and 4 are correct
Option C: 1,2 and 3 are correct
Option D: 1, 2 and 4 are correct
Correct Answer: 1,2 and 3 are correct ✔
Click for More Details
Option A: longest duration
Option B: highest cost slope
Option C: least cost slope
Option D: shortest duration
Correct Answer: least cost slope ✔
Click for More Details
Option A: 80 and 90
Option B: 90 and 80
Option C: 85 and 75
Option D: 75 and 83
Correct Answer: 75 and 83 ✔
Click for More Details
Option A: controlling the total quantity at each batch
Option B: weighing accurately, the quantity of each material for a job before mixing
Option C: controlling the quantity of each material into each batch
Option D: adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch
Correct Answer: controlling the quantity of each material into each batch ✔
Click for More Details
Option A: Hoe
Option B: Shovel
Option C: Dragline
Option D: None of the above
Correct Answer: Hoe ✔
Click for More Details
Option A: Bulldozer
Option B: Clam shell
Option C: Scraper
Option D: Dump truck
Correct Answer: Dump truck ✔
Click for More Details
Option A: 3425 kg
Option B: 5515 kg
Option C: 4350 kg
Option D: 2975 kg
Correct Answer: 5515 kg ✔
Click for More Details
Option A: 1,2,4,3,5
Option B: 1,3,2,4,5
Option C: 1,2,3,4,5
Option D: 1,3,4,2,5
Correct Answer: 1,2,3,4,5 ✔
Click for More Details
Option A: 1,2 and 4
Option B: 3,4 and 5
Option C: 1,3 and 4
Option D: 1,2 and 5
Correct Answer: 1,2 and 4 ✔
Click for More Details
Option A: total duration of project is reduced
Option B: total duration of project is increased
Option C: uniform demand of resources is achieved
Option D: cost of project is controlled
Correct Answer: uniform demand of resources is achieved ✔
Click for More Details
Option A: the fund for rebuilding a structure when its economic life is over
Option B: raised to meet maintenance costs
Option C: the total sum to be paid to the municipal authorities by the tenants
Option D: a part of the money kept in reserve for providing additional structures and structural modifications
Correct Answer: the fund for rebuilding a structure when its economic life is over ✔
Click for More Details
Option A: increase in rates of only important materials
Option B: variation in cost in materials element, labour element and petrol-oil-lubricant element
Option C: variation in total cost of the project on an ad hoc basis
Option D: rate of inflation
Correct Answer: variation in cost in materials element, labour element and petrol-oil-lubricant element ✔
Click for More Details
Option A: crash time
Option B: normal time
Option C: optimistic time
Option D: between normal time and crash time
Correct Answer: crash time ✔
Click for More Details
Option A: 1 and 4 are correct
Option B: 2 and 3 are correct
Option C: 1 and 4 are correct
Option D: 1 and 2 are correct
Correct Answer: 2 and 3 are correct ✔
Click for More Details
Option A: 3.7 years
Option B: 4.23 years
Option C: 5 years
Option D: 7.87 years
Correct Answer: 4.23 years ✔
Click for More Details
Option A: 4 days
Option B: 6 days
Option C: 10 days
Option D: 16 days
Correct Answer: 6 days ✔
Click for More Details
Option A: 50%
Option B: 84.1%
Option C: 99.9%
Option D: 100%
Correct Answer: 50% ✔
Click for More Details
Option A: Rs. 31050
Option B: Rs. 34500
Option C: Rs. 37950
Option D: Rs. 50000
Correct Answer: Rs. 31050 ✔
Click for More Details
Option A: 10000 kg
Option B: 12500 kg
Option C: 22500 kg
Option D: 5000 kg
Correct Answer: 12500 kg ✔
Click for More Details
Option A: 30 kg
Option B: 300 kg
Option C: 900 kg
Option D: 1000 kg
Correct Answer: 900 kg ✔
Click for More Details
Option A: only (i) is correct
Option B: (i) and (ii) are correct
Option C: (i) and (iii) are correct
Option D: (ii) and (iii) are correct
Correct Answer: (i) and (iii) are correct ✔
Click for More Details
Option A: 500 cum
Option B: 1000 cum
Option C: 1500 cum
Option D: 2000 cum
Correct Answer: 500 cum ✔
Click for More Details
Option A: Rs. 4,75,000/-
Option B: Rs. 5,75,000/-
Option C: Rs. 6,50,000/-
Option D: Rs. 8,50,000/-
Correct Answer: Rs. 5,75,000/- ✔
Click for More Details
Option A: equal to X
Option B: more than X
Option C: less than X
Option D: any of the above
Correct Answer: less than X ✔
Click for More Details
Option A: (ii), (iii) and (iv) are correct
Option B: (i), (ii) and (iv) are correct
Option C: (i), (iii) and (iv) are correct
Option D: (i) and (iv) are correct
Correct Answer: (i), (ii) and (iv) are correct ✔
Click for More Details
Option A: Moist loam
Option B: Good common earth
Option C: We|l blasted rock
Option D: Wet sticky clay
Correct Answer: Moist loam ✔
Click for More Details
Option A: Drag line
Option B: Hoe
Option C: Clam shell
Option D: Dipper shovel
Correct Answer: Drag line ✔
Click for More Details
Option A: reduce by 200 kg
Option B: increase by 200 kg
Option C: increase by 250 kg
Option D: reduce by 250 kg
Correct Answer: reduce by 200 kg ✔
Click for More Details
Option A: total float and free float
Option B: total float and independent float
Option C: free float and independent float
Option D: none of the above
Correct Answer: total float and free float ✔
Click for More Details
Option A: change of critical path
Option B: decrease of project completion time
Option C: increase of project completion time
Option D: all of the above
Correct Answer: all of the above ✔
Click for More Details
Option A: 9 days
Option B: 13 days
Option C: 14 days
Option D: 19 days
Correct Answer: 14 days ✔
Click for More Details
Option A: resource levelling
Option B: resource smoothening
Option C: updating
Option D: critical path scheduling
Correct Answer: updating ✔
Click for More Details
Option A: decreasing the direct cost and increasing indirect cost
Option B: increasing the direct cost and decreasing the indirect cost
Option C: increasing the direct cost and indirect cost both
Option D: decreasing the direct cost and indirect cost both
Correct Answer: increasing the direct cost and decreasing the indirect cost ✔
Click for More Details
Option A: total float
Option B: free float
Option C: interfering float
Option D: independent float
Correct Answer: independent float ✔
Click for More Details
Option A: 15 minutes
Option B: 20.143 minutes
Option C: 21 minutes
Option D: 27 minutes
Correct Answer: 21 minutes ✔
Click for More Details
Option A: is always longest
Option B: is always shortest
Option C: may be longest
Option D: may be shortest
Correct Answer: is always longest ✔
Click for More Details
Option A: free float of the activity must be zero but independent float need not be zero
Option B: independent float must be zero but free float need not be zero
Option C: free float and independent float both must be zero
Option D: free float and independent float both need not be zero
Correct Answer: free float and independent float both must be zero ✔
Click for More Details
Option A: expected time of activity A is greater than the expected time of activity B
Option B: expected time of activity B is greater than the expected time of activity A
Option C: expected time of both activities A and B are same
Option D: none of the above
Correct Answer: expected time of both activities A and B are same ✔
Click for More Details
Option A: greater than or equal to latest event time of preceding node
Option B: less than or equal to latest event time of preceding node
Option C: equal to latest event time of preceding node
Option D: less than latest event time of preceding node
Correct Answer: greater than or equal to latest event time of preceding node ✔
Click for More Details
Option A: site located
Option B: foundation is being dug
Option C: the office area is being cleaned
Option D: the invitations are being sent
Correct Answer: site located ✔
Click for More Details
Option A: most likely time
Option B: optimistic time
Option C: pessimistic time
Option D: expected time
Correct Answer: expected time ✔
Click for More Details
Option A: site investigation started
Option B: sessional work completed
Option C: bus starts from Jaipur
Option D: class is being attended
Correct Answer: class is being attended ✔
Click for More Details
Option A: interdependencies of activities
Option B: project progress
Option C: uncertainties
Option D: all of the above
Correct Answer: all of the above ✔
Click for More Details